Free P6 schedule health check
Upload a Primavera P6 export and find out, in seconds, whether the schedule can be trusted: a grade from A to F, more than 30 checks in plain words (the 14 points of the DCMA assessment and more than 15 of our own), and the list of activities behind every problem. Made for planners, and for the project managers, contract administrators and clients who have to read their work.
Sign up with your email. 7-day free trial of everything, then the schedule health check stays free. Your file is stored in Australian data centres and only your space sees it.
612 activities
| Missing logic | 9 of 486 open activities | watch |
| Hard constraints | 31 of 486 | fail |
| Lags | 22 of 1,140 links | pass |
| High float | 57 of 486 | fail |
| Critical path test | finish moves with the test | pass |
What you get
A grade from A to F: A from 90 points out of 100, B from 80, C from 70, D from 60, and F below that. A severe fault (circular logic, negative float, invalid dates, too many open ends, a failed critical path test) caps the grade whatever the points say. Under the grade, more than 30 checks: the 14 points of the DCMA assessment and more than 15 of our own, each with its limit, the activities that fail it and how to fix it in P6. Where you also load a baseline file, the baseline checks (missed baseline finishes with the BEI, CPLI) come on.
The 14 DCMA points
Some of our own
How it works
- 1
Sign up with your email
No password: a one-time code is emailed to you. Your account is ready in a minute, with a 7-day free trial of everything.
- 2
Upload the XER export
In P6 choose File, Export, XER. Load the file with the Load button; a P6 XML or Microsoft Project file also works.
- 3
Read the result in seconds
The grade, every check and the activities behind each one, with an Excel export. Your file is stored in Australian data centres and only your space sees it.
Who it is for
Planners
Check a baseline or a monthly update before it goes out, with the list of activities to fix in P6.
Project managers
Know whether the programme you are managing to can be trusted, without opening P6.
Contract administrators
Review a contractor's baseline or update against the usual yardstick, with the evidence listed.
Clients
Ask for the XER and see for yourself how sound the programme is before you accept it.
Questions people ask
Is it really free?
Yes. Every new account starts with a 7-day free trial of everything GanttMind does. When the trial ends, the schedule health check and your files stay free: you can keep uploading XER files (up to 25 MB each, 3 a day, 2 projects) and reading the result. The other pages ask for a quote.
What happens after the 7 days?
Your account moves to the free plan by itself. Nothing is deleted. The Health tab and the Files page keep working; Reporting, Scheduling, Risk and Delay analysis need a paid plan, which we quote per team.
Which files can I upload?
A Primavera P6 XER export (File, Export, XER in P6). A P6 XML or Microsoft Project file also loads. One file is enough; add a baseline file and the baseline checks (missed baseline finishes with the BEI, CPLI against the baseline finish) come on as well.
Is my schedule safe?
Your file sits in a private store in Australian data centres (Sydney). Only the people you invite to your space can see it. It is never shown to other customers, sold or used to train AI models, and you can delete it yourself at any time.
Do you change my file?
No. The check reads the dates, floats and logic P6 saved in the file and reports on them. Your XER is never edited, and you fix anything in P6 as you normally would.
What is the DCMA 14-point assessment?
A set of 14 schedule checks published by the United States Defense Contract Management Agency (missing logic, leads, lags, relationship types, hard constraints, high float, negative float, high duration, invalid dates, resources, missed tasks, the critical path test, CPLI and BEI). It has become the usual yardstick for schedule quality. We run those 14 and more than 15 checks of our own that we use when we review programmes: more than 30 in all.
How is this different from P6's own Schedule Log or Check Schedule?
P6's Schedule Log lists what happened when the schedule was calculated. P6 EPPM's Check Schedule runs similar counts for licensed P6 users; the health check grades the result, lists the activities behind every check and works for people who do not have P6 open: a project manager, a contract administrator or a client.
Can I check a contractor's programme?
Yes. Ask for the XER export of the programme, upload it and read the grade and the lists. Clients and superintendents can use the checks when they review a baseline or a monthly update.